Jakarta, 27-29 SEPTEMBER 2010 Workshop XL Axiata - Ericsson.

Presentasi serupa


Presentasi berjudul: "Jakarta, 27-29 SEPTEMBER 2010 Workshop XL Axiata - Ericsson."— Transcript presentasi:

1 Jakarta, SEPTEMBER 2010 Workshop XL Axiata - Ericsson

2 Ericsson Confidential2010-Sep2 AGENDA ›DAY 1 –Process Overview –Project Flow Overview –Product Knowledge Sharing –Design Knowledge Sharing ›DAY 2 –MINI-LINK TN Operation (Theory) ›DAY 3 –MINI-LINK TN Operation (Hands-on)

3 Process Overview

4 Ericsson Confidential2010-Sep4 Available NRO SERVICES IN ERICSSON Project Management Business Solutions Network Planning & Design Consulting Network Build Network Integration Network & Site Optimization Operations & Support Turnkey Network Rollout

5 Ericsson Confidential2010-Sep5 General Process Overview Activities: Perform survey result review Perform detailed link design Perform link-budget calculations Perform propagation and interference analysis (Frequency Analysis) Perform connection / routing plan Perform detailed DCN design Perform synchronization plan Create: Adjusted equipment list Create detailed design specification Design overview report Detailed Design Startup & Information Gathering Acceptance & Conclusion Activities: Review contract agreement Scope of MW network deployment Network topology Quality and availability allocation Network equipment information Existing NW, Site Infrastructure Create: Project time plan Requirement specification Network Execution Site & Path Survey Activities: Equipment installation, setting, and commissioning Interference level check Traffic integration Functionality test Troubleshooting during project execution Performance test Acceptance Test Procedure (ATP) Create: Method / Implementation Procedure ATP document Activities: Map and field survey, Perform site engineering survey Perform Line-Of-Sight survey, Radio Frequency Investigation Path analysis, interference risks, alternative solutions Proposals for equipment installation Create: MW Transmission Survey Report Site Layout and Requirement Activities: Documentation Closing activities Project evaluation Create: Acceptance Certificate Lesson learned Solution Design Activities: Define network topologies Perform network dimensioning Perform nominal design Define the proper HW and SW for each link Create: Present nominal network design Present the solution specification Preliminary Equipment list

6 Ericsson Confidential2010-Sep6 Solution Design Activities ›Customer Contract Agreement ›Customer requirement and guideline ›Recommendation from Standard-body and Regulator ›Ericsson guideline and recommendation ›Product package and information ›Nominal plan and required capacity ›Existing network data and site information INPUT ›Preliminary network design layout ›Preliminary equipment list (BoQ) ›Network connection type / scenario ›Nominal plan sites / links ›Guideline and recommendation ›Solution specification Define network topology Perform network dimensioning Perform nominal design Define the proper HW and SW for each link Perform network connection scenario Allocate quality and target requirement ACTIVITIES OUTPUT

7 Ericsson Confidential2010-Sep7 Design Activities ›Customer Contract Agreement ›Ericsson guideline and recommendation ›Solution specification –Preliminary network design –Preliminary equipment list –Nominal plan ›Survey result ›Existing network data ›Radio design document and requirement INPUT ›Detailed Design document ›Network topology ›Adjusted equipment list ›Path Performance Report ›Frequency plan ›Traffic connection plan ›Node configuration diagram ›Detailed DCN IP address ›Synchronization plan ›Design database Review Transmission survey report Design Review Meeting (DRM) Adjust equipment list (BoQ) Performance calculation Frequency assignment plan Traffic routing plan Detail DCN design Synchronization plan Network database ACTIVITIES OUTPUT TopologyPerformance ReportConnection PlanDCN

8 Ericsson Confidential2010-Sep8 Network Execution Activities ›Customer Contract Agreement ›Ericsson standard installation guideline and recommendation ›Plan specification for equipment installation ›Site installation document ›Detailed design document ›Site readiness ›Supporting, such as work permit, key access, etc. INPUT ›Equipment installed ›Equipment configured ›Method / Implementation procedure ›MINI-LINK on air ›Traffic integration, ready for service ›Implementation progress report ›ATP document Equipment installation, setting, and commissioning Interference level check Traffic integration Network Element integration to NMS Functionality test Troubleshooting during project execution Performance test Acceptance Test Procedure (ATP) ACTIVITIES OUTPUT

9 Project Flow Overview

10 Ericsson Confidential2010-Sep10 Sequencing Implementation Test & Commissioning AssignmentAcceptanceImplementation Preparation Material Dismantle & Return C-Module Validation E2E Integration Node B Announce Implementation MLTN Support Node B Integration Monthly Target: XL CPMO provide Overall target List every Month XL CPMO provide tentative execution date on each monthly Target

11 Ericsson Confidential2010-Sep11 Test & Commissioning Assignment Activities: Confirmation Work Order execution date by from XL FOP Review contract agreement (EWO) Check EWO Number Check PO Scope of MW network deployment (BOQ) Network topology Information Existing MW, Site Infrastructure AcceptanceImplementation Activities: Material checklist Request site access to each area Re-check E1 cross connection informed by FOP Install ML-TN magazine and all modules Record data existing (from ML- E) Activities: Check ML-TN installation to meet Ericsson Standard Check ML-TN configuration Functional Test Install License Key File (LKF) Fill in ATP document ML-TN can be monitored from DCN server Preparation Material Dismantle & Return C-Module Activities: Confirm execution time plan Request Site Installation Document PQR/Link Budget, Existing Traffic Capacity Data Cross Connection IP Address, Layout Equipment, Site Address Review given documentation Request ATND for respective Node-B (VLAN Iub, OAM, OSN port allocation) Activities: Dismantle ML-E from sites Negative reservation to XL Warehouse regarding material return Send material to XL Warehouse Activities: Create C-Module and Submission Activities: Basic commissioning of ML-TN Interference test of Frequency Traffic Migration Advanced commissioning: Static Routing, PDH-IME/RL-IME, VLAN BER Test E1 24 hours Ethernet Measurement (RFC 2544, Jitter VLAN end to end validation to support Node-B Save Report and Load Configuration for Backup Save License Request File (LRF) Project Activites

12 Ericsson Confidential2010-Sep12 Assignment Activities: Confirmation Work Order execution date by from XL FOP Review contract agreement (EWO) Check EWO Number Check PO Scope of MW network deployment (BOQ) Network topology Information Existing MW, Site Infrastructure Need Improvement (XL): Need detailed SOW, to give valid configuration of requirement on network; MW links capacity Config protection (1+0 or 1+1) Need valid and updated TRM network link route for each Node-B, to have end to end network topology. Need Improvement (EID): EID to escalate readiness issue (detail EWO data package) to all respective PIC EID to review the EWO Package Assignment Activities and Improvement

13 Ericsson Confidential2010-Sep13 Need Improvement (XL): Need Site Installation Document (SID) from XL: PQR / Link Budget Existing Traffic Capacity information VALID Data of E1 cross connection IP Address Layout equipment Preparation Activities: Confirm execution time plan Request Site Installation Document PQR/Link Budget, Existing Traffic Capacity Data Cross Connection IP Address, Layout Equipment, Site Address Review given documentation Request ATND for respective Node-B (VLAN Iub, OAM, OSN port allocation) Need Improvement (EID): Improve commitment on execution schedule Improve coordination for required support and data Preparation Activities and Improvement

14 Ericsson Confidential2010-Sep14 Need Improvement (EID): EID team need to start at coordination period time (08:00 AM - 10:00 AM at XL Center) Improve troubleshooting if problem exist and minimize downtime Proper procedure for performance issue / alarm clearance of existing link before upgrade capacity / swap Implementation Activities: Coordination to each area regarding execution, material readiness Request site access to each area Re-check E1 cross connection informed by FOP Install ML-TN magazine and all modules Record data existing (from ML-E) Need Improvement (XL): XL need to validate data E1 cross connection AMM/Magazine placement design (No temporary place: floor, chair, box) Implementation Activities and Improvement

15 Ericsson Confidential2010-Sep15 Need Improvement (EID): BER Test will be done if there are free E1. If no free E1, refer to ML-TN link performance. Ethernet measurement will be done for each ML-TN hop refer to RFC 2544 Proper procedure for fallback issue, include target for problem solving Activities: Basic commissioning of ML-TN Interference test of Frequency Traffic Migration Advanced commissioning: Static Routing, PDH-IME/RL-IME, VLAN BER Test E1 24 hours Ethernet Measurement (RFC 2544, Jitter VLAN end to end validation to support Node-B Save Report and Load Configuration for Backup Save License Request File (LRF) Test & Comm Need Improvement (XL): In XL MBB project, most swap increase the bandwidth, so we have to re-checked the interference level. XL will provide new frequency allocation if interference occurred Need Ethernet capacity design for each hops from XL. FOP will responsible to follow up static routing issue at DCN router to speed up ML-TN monitoring. End to end validation will be done by transport measurement (Node-B – MLTN – OSN/MSTP – Router - RNC). Test & Commissioning Activities and Improvement

16 Ericsson Confidential2010-Sep16 Need Improvement (EID): Team capacity and availability to support ATP as propose schedule Awareness on un-proper installation, understand on impact and quality installation standard Acceptance Activities: Check ML-TN installation to meet Ericsson Standard Check ML-TN configuration Functional Test Install License Key File (LKF) Fill in ATP document ML-TN can be monitored from DCN server Need Improvement (XL): ATP need to be scheduled maximum 7 days after ML-TN stated On Air (If ML-TN have no alarm). Action to rectify installation problem due to space and material issue (example: AMM installed at the floor, temporary 1+0) Follow up all issue regarding lack material if any on site planning to ATP. Acceptance Activities and Improvement

17 Ericsson Confidential2010-Sep17 Need Improvement (EID): ML-E need to be dismantled after verification function and reliability of MLTN passed, maximum 3 days after ML-TN On Air and material directly send to XL Warehouse. Material Return Activities: Dismantle ML-E from sites Negative reservation to XL Warehouse regarding material return Send material to XL Warehouse Need Improvement (XL): Negative Reservation (return material acknowledgement), XL need to provide at least 2 days after request received. This will improve lead time of closing ATP Need to simplify location storage of dismantle material to speed up H/O process. Such as, put dismantled material to remote XL W/H. MATERIAL RETURN Activities and Improvement

18 Ericsson Confidential2010-Sep18 Need Improvement (EID): C-Module need to be finished as soon as possible, maximum 14 days (calendar days) after ATP done. C-Module Activities: Create C-Module and Submission Need Improvement (XL): Need to simplify closing ATP process signing and approval. Such as, collocated approval, material storage and documentation handover in one area in one time ( base on agreed schedule) Documentation Activities and Improvement

19 Ericsson Confidential2010-Sep19 Validation E2E Integration Node B Announce Activities: Validation E2E Hut to RNC should ready before Integration Setting Up router (IP) Setting Up OSN (port VLAN) Validation E2E Hut to End site Setting Up VLAN ID E2E Measurement from Node B to RNC. Activities: After Validation E2E valid activity will continue to support integration NODE B into Network. Ensure MAC Address Node B and OSN can read from MLTN. Make sure data can loading into Node B from RNC and Node B function properly Activities: Integration success and No Alarm ML TN can be monitored from server If both Criteria met, the MLTN integration is declared completed Sequencing Support Integration

20 Ericsson Confidential2010-Sep20 Validation E2E Activities: Validation E2E Hut to RNC should ready before Integration. Validation E2E Hut to End site Setting Up VLAN ID Need Improvement (XL): Active port and VLAN ID setup readiness on OSN device, require earlier or faster response Bandwidth Ethernet traffic on OSN should be properly. Measurement End to end link from Node B to RNC to make sure no issue between TN to RNC Validation E2E Hut to RNC should ready before Integration Setting Up the traffic routing from HUT to RNC (IP) Setting Up OSN (port VLAN) Need Improvement (EID): Accelerate transmission link validation for faster Node-B integration Improve coordination for port assignment and traffic availability on existing XL network Validation END to END Activites and Improvement

21 Ericsson Confidential2010-Sep21 Integration Node B Activities: Ensure MAC Address Node B and OSN can read from MLTN. Make sure data can loading into Node B from RNC and Node B function properly Need Improvement (XL-EID): Improve coordination between transmission and radio team to accelerate Node-B integration, start form early target setup until execution Integration Node-B Activities and Improvement

22 Ericsson Confidential2010-Sep22 Announce Activities: Integration success and No Alarm ML TN can be monitored from server If both Criteria met, the MLTN integration is declared completed Annouce integration result Activites and Improvement

23

24 Ericsson Confidential2010-Sep24 NETWORK Topology ›The overall view of the network –Network view database –Transmission link database

25 Ericsson Confidential2010-Sep25 Path Performance Report ›Link budget calculation ›Frequency assignment plan ›Propagation analysis –Line of sight –Path profile –Fading analysis for diversity –Optimum antenna placement for diversity

26 Ericsson Confidential2010-Sep26 CONNECTION PLAN / Traffic Routing ›Network capacity dimensioning and slot allocations ›Information about traffic routing plan ›Inform about detail link capacity and potential capacity

27 Ericsson Confidential2010-Sep27 DCN Plan ›IP DCN for Transmission Network Management System ›IP Network level requirement and structured assignment per network cluster ›Breakdown to detail IP address assignment for each Network Element ›Design DCN using OSPF routing protocol