Presentasi sedang didownload. Silahkan tunggu

Presentasi sedang didownload. Silahkan tunggu

DIGUNAKAN UNTUK: MENGEVALUASI PENJADWALAN & PENGEMBANGAN, MENGUKUR & MENGENDALIKAN KEMAJUAN BERBAGAI KEGIATAN DALAM SUATU PROYEK YAITU DG MELALUI PENENTUAN.

Presentasi serupa


Presentasi berjudul: "DIGUNAKAN UNTUK: MENGEVALUASI PENJADWALAN & PENGEMBANGAN, MENGUKUR & MENGENDALIKAN KEMAJUAN BERBAGAI KEGIATAN DALAM SUATU PROYEK YAITU DG MELALUI PENENTUAN."— Transcript presentasi:

1 DIGUNAKAN UNTUK: MENGEVALUASI PENJADWALAN & PENGEMBANGAN, MENGUKUR & MENGENDALIKAN KEMAJUAN BERBAGAI KEGIATAN DALAM SUATU PROYEK YAITU DG MELALUI PENENTUAN LINTASAN KRITIS (CRITICAL PATH) & FLOAT (LINTASAN TDK KRITIS YGMASIH PUNYA WAKTU UTK BISA TERLAMBAT. FLOAT MEMBERIKAN KELONGGARAN WAKTU & ELASTISITAS PD SEBUAH NET WORK)

2 SIMBOL-SIMBOL YG DIGUNAKAN: MENYATAKAN SEBUAH AKTIVIAS YG MEMERLUKAN WAKTU TERTENTU (DURASI) UTK BERJALAN DR SATU NODE KE NODE LAINNYA, & MENGHABISKAN RESOURCES. KEPALA ANAK PANAH MENUNJUKKAN ARAH TIAP AKTIVITAS, & ARAHNYA DR KIRI KE KANAN MENUNJUKKAN NODE (EVENT / KEJADIAN), DARI SATU KEJADIAN KEJADIAN LAINNYA MENYATAKAN KEGIATAN DUMMY (SEMU), KEGIATAN SEMU TIDAK MEMPUNYAI DURASI KRN TIDAK MEMAKAI/MENGHABISKAN RESOURCES

3 CONTOH: INITIAL EVENT TERMINAL EVENT

4 SIFAT KETERGANTUNGAN DR. KEGIATAN-KEGIATAN: 1) JIKA KEGIATAN A HRS DISELESAIKAN DAHULU SEBELUM KEGIATAN B DPT DIMULAI. KEGIATAN A DPT DITULIS (1,2) & B (2,3) 123 AB 2) JIKA KEGIATAN C,D & E HRS DISELESAIKAN DAHULU SEBELUM KEGIATAN B DPT DIMULAI D E C F

5 3) JIKA KEGIATAN K & L HRS SELESAI SEBELUM KEGIATAN M DPT DIMULAI, TETAPI KEGIATAN N SUDAH BOLEH DIMULAI BILA KEGIATAN L SUDAH SELESAI K LN M 4) JIKA KEGIATAN P, Q & R MULAI & SELESAI PD LINGKARAN KEJADIAN YG SAMA. 33

6 LATIHAN (LEVIN, P : AKTIVITASP ANONE BA CA DB,C EC FD GE,F P = PREDECESSORS (AKTIVITAS YG TELAH DILALUI) AKTIVITASP ANONE B CA,B D EC FC,D GF 1)2) AKTIVITASt 1 – 24 2 – 32 2 – 41 3 – 45 3 – 66 4 – – )

7 LATIHAN (LEVIN, P : AKTIVITASPTIME ANONE6 BA8 CA4 DB9 EC2 FD7 P = PREDECESSORS (AKTIVITAS YG TELAH DILALUI) AKTIVITASPTIME ANONE4 B 9 CA3 DB8 EB7 FD2 GE5 5)4)

8 NOTASI YG DIGUNAKAN: NTSURAIAN TE =EARLIEST EVENT OCCURRENCE TIME (SAAT TERCEPAT TERJADINYA EVENT) TL =LATEST EVENT OCCURANCE TIME (SAAT TERLAMBAT TERJADINYA EVENT) EF =EARLIEST ACTIVITY FINISH TIME (SAAT TERCEPAT DISELESAIKANNYA AKTIVITAS) ES =EARLIEST ACTIVITY START TIME (SAAT TERCEPAT DIMULAINYA AKTIVITAS) LF =LATES ACTIVITY FINISH TIME ( SAAT TERLAMBAT DISELESAIKANNYA AKTIVITAS) LS =LATEST ACTIVITY START TIME (SAAT TERLAMBAT DIMULAINYA AKTIVITAS) t =AKTIVITY DURATION TIME (WAKTU YG DIPERLUKAN UNTUK SUATU AKTIVITAS) S =TOTAL SLACK / TOTAL FLOAT SF =FREE SLACK / FREE FLOAT

9 ASUMSI : 1)PROYEK HANYA PUNYA SATU INITIAL EVENT & SATU TERMINAL EVENT 2)SAAT TERCEPAT TERJADINYA INITIAL EVENT ADALAH HARI KE 0 3)SAAT PALING LAMBAT TERJADINYA TERMINAL EVENT ADALAH TL=TE CARA PERHITUNGAN: MENGHITUNG SAAT PALING CEPAT TERJADINYA EVENT & SAAT PALING CEPAT DIMULAINYA SERTA DISELESAIKANNYA AKTIVITAS- AKTIVITAS (TE, ES & EF) KEBALIKAN DR YG DI ATAS LAMBAT (TL, LS & LF) a b c SAAT PALING LAMBAT TERJADINYA EVENT SAAT PALING CEPAT TERJADINYA EVENT a = NO EVENT b = TE PERHITUNGAN MAJU c = TL PERHITUNGAN MUNDUR

10 A 4 E F J H 11 G 9 7 C D 15 I 3 K5 8 B 6

11 A 4 E F J H 11 G 9 7 C D 15 I 3 K5 8 B

12 A 4 E F J H 11 G 9 7 C D 15 I 3 K5 8 B

13 A 4 E F J H 11 G 9 7 C D 15 I 3 K5 8 B t = 0

14 AKT (I, j)t (I, j)PALING CEPAT PALING LAMBAT TOTAL FLOAT (S) FREE FLOAT (SF) ESEFLSLF ( 0, 1 ) ( 0, 2 ) *) ( 0, 3 ) ( 1, 4 ) ( 2, 4 ) ( 2, 5 ) *) ( 3, 6 ) ( 4, 8 ) ( 5, 6 ) *) ( 5, 8 ) ( 6, 7 ) *) ( 7, 8 ) *) EF – ES - t (LS – ES) ATAU (LF – EF)

15


Download ppt "DIGUNAKAN UNTUK: MENGEVALUASI PENJADWALAN & PENGEMBANGAN, MENGUKUR & MENGENDALIKAN KEMAJUAN BERBAGAI KEGIATAN DALAM SUATU PROYEK YAITU DG MELALUI PENENTUAN."

Presentasi serupa


Iklan oleh Google