This presentation uses a free template provided by FPPT.com MR. NUGROHO PLAN TROPICAL RENEWABLE ENERGY CENTER
This presentation uses a free template provided by FPPT.com OUTLINE Load Profile Annual Load Cost Multi Year Probability Photovoltaic as a Solution
This presentation uses a free template provided by FPPT.com LOAD PROFILE HourLoad (kW) – – – – – – – – – – – – HourLoad (kW) – – – – – – – – – – – –
This presentation uses a free template provided by FPPT.com ANNUAL LOAD COST (GRID ONLY) MonthCost (Rupiah) January Rp February Rp March Rp April Rp May Rp June Rp July Rp August Rp September Rp October Rp November Rp December Rp Annual Rp Multi Year Probability makes us to think about the changes that can occur over the lifetime of the project. The Multi Year Probability is consist of Grid Price Escalation and Load Growth. We usually specify the Grid Price Escalation and Load Growth in terms of percentage each year (%/year)
This presentation uses a free template provided by FPPT.com MULTI YEAR PROBABILITY For this project, we have already found a data statistic about Load Growth and Grid Price Escalation. For DC Load increased by 5% per year and AC Load decreased by 1% per year, and for Grid Price Escalation is about 5 – 7% per year.
This presentation uses a free template provided by FPPT.com MULTI YEAR PROBABILITY YearAnnual Cost Rp Rp Rp Rp Rp YearAnnual Cost Rp Rp Rp Rp Rp Load Growth1% Grid Price Escalation5% YearAnnual Cost Rp Rp Rp Rp Rp YearAnnual Cost Rp Rp Rp Rp Rp Total Biaya Pembayaran Listrik selama 20 tahun Rp YearAnnual Cost Rp Rp Rp Rp Rp
This presentation uses a free template provided by FPPT.com PHOTOVOLTAIC AS A SOLUTION
This presentation uses a free template provided by FPPT.com PHOTOVOLTAIC AS A SOLUTION On This Project, We offer Trans-Mart Bogor to use Photovoltaic to Reduce their Electricity Bill over 20 years. Load Growth5 % Grid Price Escalation1 % Photovoltaic4 kW PV Degradation0.5 % YearAnnual Cost Rp11,327, Rp11,970, Rp12,742, Rp13,476, Rp14,259, YearAnnual Cost Rp15,095, Rp15,988, Rp16,944, Rp17,966, Rp19,061, YearAnnual Cost Rp20,235, Rp21,495, Rp22,848, Rp24,303, Rp25,867, YearAnnual Cost Rp27,552, Rp29,368, Rp31,328, Rp33,443, Rp35,730, Total Cost Rp YearAnnual Cost Rp Rp Rp Rp Rp
This presentation uses a free template provided by FPPT.com PHOTOVOLTAIC AS A SOLUTION YearAnnual Saving Rp Rp Rp Rp Rp YearAnnual Saving Rp Rp Rp Rp Rp YearAnnual Saving Rp Rp Rp Rp Rp YearAnnual Saving Rp Rp Rp Rp Rp Total Saving Pembayaran Listrik selama 20 tahun Rp Load Growth5 % Grid Price Escalation5 % Photovoltaic4 kW PV Degradation0.5 % YearAnnual Saving Rp Rp Rp Rp Rp
This presentation uses a free template provided by FPPT.com COMPARISON BETWEEN ONLY GRID & GRID+PV LOAD GROWTH 1% - GRID PRICE ESCALATION 5%
This presentation uses a free template provided by FPPT.com COMPARISON BETWEEN ONLY GRID & GRID+PV LOAD GROWTH 1% - GRID PRICE ESCALATION 5%
This presentation uses a free template provided by FPPT.com COMPARISON BETWEEN ONLY GRID & GRID+PV LOAD GROWTH 1% - GRID PRICE ESCALATION 5%
This presentation uses a free template provided by FPPT.com BREAK EVEN POINT BEP is the point at which total cost (Capital Cost and Replacement Cost) and total revenue are equal. BEP is usually called expected time of return. Capital Cost (PV 4 kW, Converter 4 kW) ; Replacement Cost (Converter 4 kW) BEP akan terjadi pada tahun ke - 14
This presentation uses a free template provided by FPPT.com TOTAL REVENUE OVER 20 YEARS (5% & 6%) TOTAL SAVING ELECTRICITY BILL OVER 20 YEARS – CAPITAL COST – REPLACEMENT COST Rp Rp – Rp = Rp Notes : Capital Cost consist of (PV 4 kW + Converter 4 kW) + Replacement Converter 4 kW