Bandar lampung 8-10 januari 2014 RAPAT KOORDINASI TRIWULAN IV-2013 PT. PLN (PERSERO) PEMBANGKITAN SUMBAGSEL BIDANG PRODUKSI Peningkatan Pengendalian Proses Bisnis untuk Mencapai World Class Services Bandar lampung 8-10 januari 2014
PREDIKSI REALISASI KINERJA 2013
EFOR 2013 >> MASALAH Target 1,8 | Realisasi 4,55 No UNIT Kontribusi EFOR 1 PLTU Ombilin # 1 12,75% 0,58 Derating 2 PLTU Bukit Asam #2 11,64% 0,53 3 PLTU Bukit Asam #3 6,15% 0,28 No UNIT Kontribusi EFOR 1 PLTU Tarahan #4 12,08% 0,55 Gangguan 2 PLTU Tarahan #3 6,81% 0,31 3 PLTU Bukit Asam #2 8,57% 0,39 4 PLTG Pauhlimo #3 7,03% 0,32
SDOF 2013 >> MASALAH Target 1,5 | Realisasi 1,79 NO Jml trip 1 2 Unit Jml trip 1 PLTG Borang #3 (LM 2000) : 10 kali 2 PLTGU Indralaya ST 1.0 8 3 PLTU Bukit Asam #2 9 4 PLTU Bukit Asam #3 5 PLTU Bukit Asam #4 7 6 PLTU Tarahan #3 PLTU Tarahan #4 11 PLTD Tarahan #4 PLTG Pauh Limo #3 PLTU Ombilin #1 Target SdOF : 1,5 Realisasi SdOF : 1,79 Jumlah unit : 82 unit Equivalent jumlah kali trip : 123 kali Realisasi jumlah kali trip : 147 kali
2013 – Penyerapan Gas 2013 2014 realisasi (BBTU) target (BBTU) % SKRM Catatan : Gangguan PLTG Keramasan 2 sejak Februari 2013 telah menurunkan penyerapan gas sebesar 4 BBTUD Gangguan PLTG AKE sejak Agustus 2013 telah menurunkan kemampuserapan gas s.d. 34 BBTUD di PL Keramasan 2013 2014 realisasi (BBTU) target (BBTU) % SKRM 24.920 32.052 78 19.452 SJMB 16.799 10.741 156 18.987 ∑ 41.721 42.793 97 38.439
2014 – Penyerapan Gas
Gas Make Up Borang GMU s.d. November 2013 5.246.929 MMBTU
Gas Make Up Keramasan GMU s.d. November 2013 2.454.271 MMBTU
2013 – Efisiensi Working Capital Data sementara, masih menunggu hasil rekon keuangan dan update SAP Tambahan material belum terpakai : 32M; coil bar; PLTU Ombilin 31M; mandatory part; PLTP Ulubelu 13M; TIV; PLTA Maninjau 11M; turbine rotor; PLTU Bukit Asam
REKAPITULASI RENCANA dan REALISASI OUTAGE MANAGEMENT 2013 NO SEKTOR RENCANA REALISASI TW I TW II TW III TW IV JML 1 SBKT 2 3 9 4 SOMB 5 SJMB 6 SKRM SBAM SBKL 7 SBDL 8 STAR STIR JMLH 12 13 43 26
GRAFIK RENCANA dan REALISASI OUTAGE MANAGEMENT 2013 TOTAL RENCANA = 43 TOTAL REALISASI = 26 60,47 %
REKAPITULASI OUTAGE MANAGEMENT 2013
GRAFIK RENCANA dan REALISASI OUTAGE MANAGEMENT 2013 TOTAL RENCANA = 43 TOTAL REALISASI = 26 60,47 %
Rencana Pemeliharaan Periodik 2014
PEMBANGKIT YANG MENGALAMI PERPANJANGAN DURASI PELAKSANAAN OVERHAUL 1. SEKTOR KERAMASAN : PLTG TALANG DUKU, PEKERJAAN MAJOR INSPECTION (MI), RENCANA DURASI 45 HARI, REALISASI 163 HARI KETERLAMBATAN SELAMA 118 HARI, KARENA ADA PERBAIKAN SECOND STAGE NOZZLE dan GANGGUAN SISTIM CONTROL. 2. SEKTOR OMBILIN : PLTG PAUHLIMO # 3, PEKERJAAN HOT GAS PATH INSPECTION (HGPI) RENCANA DURASI 35 HARI, REALISASI 74 HARI KETERLAMBATAN 39 HARI, KARENA ADANYA PEKERJAAN REBABIT BEARING TURBIN.
MONITORING PELAPORAN OUTAGE MANAGEMENT 2013 UNIT SEKTOR PRE OUTAGE OUTAGE EXECUTION POST OUTAGE KETERANGAN 1 BUKIT TINGGI ada Blm msk 2 OMBILIN 3 JAMBI Msk PLTD_4 dan PLTG_2 4 KERAMASAN 5 BUKIT ASAM 6 BENGKULU Srt 119/SBKL/13, tgl 11-10-13 7 BANDAR LAMPUNG 8 TARAHAN 9 TELUK SIRIH Blm ada HAR Periodik
STAR,SBAM, SKRM (PL KERAMASAN) SOMB (PL PAUH LIMO & OMBILIN) PERINGKAT PROPER TTAHUN 2013 BERDASARKAN UU 32 TAHUN 2009 E M A S H I J A U PL INDRALAYA-SKRM B I R U STAR,SBAM, SKRM (PL KERAMASAN) MERAH SOMB (PL PAUH LIMO & OMBILIN)
REALISASI Bayar S/D NOP. 2013 PROSENTASE PENYERAPAN REALISASI PENYERAPAN ANGGARAN 2013 (dalam ribuan Rp) SEKTOR PENETAPAN RKAP 2013 RUTIN KHUSUS JUMLAH SKRM 43.300.884 169.950.745 213.251.629 SBDL 49.376.250 76.193.136 125.569.386 STAR 40.000.000 139.047.742 179.047.742 SBAM 76.605.716 135.697.980 212.303.696 SBKL 10.685.660 45.832.483 56.518.143 SJMB 13.578.771 107.372.849 120.951.620 SOMB 66.556.286 204.919.573 271.475.859 SBKT 11.246.442 26.461.469 37.707.911 STIR KITSBS 9.143.962 TOTAL 320.493.971 905.475.977 1.225.969.948 SEKTOR REALISASI Bayar S/D NOP. 2013 RUTIN KHUSUS JUMLAH SKRM 35.211.349 46.919.118 82.130.467 SBDL 29.178.141 17.581.870 46.760.011 STAR 33.344.648 27.746.684 61.091.332 SBAM 66.950.504 45.814.341 112.764.845 SBKL 16.450.996 4.382.710 20.833.706 SJMB 9.608.207 45.965.413 55.573.620 SOMB 65.886.840 43.977.747 109.864.587 SBKT 14.971.270 7.024.870 21.996.140 STIR KITSBS 3.423.556 TOTAL 275.025.511 239.412.753 514.438.264 SEKTOR PROSENTASE PENYERAPAN RUTIN KHUSUS TOTAL SKRM 81,32 27,61 38,51 SBDL 59,09 23,08 37,24 STAR 83,36 19,95 34,12 SBAM 87,40 33,76 53,11 SBKL 153,95 9,56 36,86 SJMB 70,76 42,81 45,95 SOMB 98,99 21,46 40,47 SBKT 133,12 26,55 58,33 STIR 0,00 KITSBS 37,44 85,81 26,44 41,96
Kapasitas Terpasang dan Jumlah Pegawai
Rasio Pegawai per Pembangkit Kapasitas (MW) Rasio (MW/Peg) Total Rasio Pegawai KITSBS 1,83 MW/Pegawai
Rasio Pegawai per Sektor Kapasitas (MW) Rasio (MW/Peg) Total Rasio Pegawai KITSBS 1,83 MW/Pegawai
4,8 MW/Peg. 1,83 MW/Peg. ... Next Step ! Otomatisasi sistem operasi Peningkatan Pengendalian Proses Bisnis untuk Mencapai World Class Services 4,8 MW/Peg. Otomatisasi sistem operasi Penambahan unit kapasitas besar Restrukturisasi organisasi Alih daya pekerjaan Integrasi administrasi Job enrichment Peningkatan kapabilitas SDM 1,83 MW/Peg.
Terima Kasih
total tambahan sebesar 634 MW Suplemen 3 Tambahan Kapasitas 2014 PLTU Teluk Sirih 1 - 2 2 x 112 MW (Jan & Apr-14) PLTG Sewa Pyslcah 30 MW (Feb-14) 50 MW (Jun-14) PLTGU Keramasan 2 x 40 MW (Jan-14) PLTG Sewa Krmsan 50 MW (Jul-14) PLTU Tarahan 5 - 6 2 x 100 MW (???) total tambahan sebesar 634 MW
PLTMG Kerta Bumi Teknindo Suplemen 4 Pasokan Gas Jambi 18 MRS Simp. Bayat MRS Tempino GRISSIK (Cophi) pipa TGI Grissik - Duri DURI BBTUD Pemasok Waktu 18 EHK 25 MW Pemasok 6 x 5.2 PLTD Payo Selincah 2 x 30 PLTG Batanghari 1 & 2 18 PLTG Batanghari 3 2 x 50 PLTG BOT Eramas Pusat Listrik : Payo Selincah 2 5 BBTUD Pemasok Waktu 25 PTJM 9-Feb-2019 5 EMP Gelam 14-Mei-2017 2 UBEP MW Pemasok 90 PLTMG Sei Gelam 12 PLTMG Kerta Bumi Teknindo Pusat Listrik : Sei Gelam
Suplemen 5 Pasokan Gas Keramasan dari Pertagas BBTUD Pemasok Waktu 17 Medco April 2015 MW Pembangkit 45 GT 1.1 Indralaya 38 GT 1.2 Indralaya 40 ST 1.0 Indralaya Pusat Listrik : Indralaya 15 14 3 3 x 18 PLTG Jakabaring 1,2,3 Pusat Listrik : Jakabaring PDPDE Okt 2021 Pertamina Nov 2015 Okt 2014 2 x 40 PLTGU Keramasan 2 x 15 PLTG Keramasan 3,4 2 x 10 PLTG Keramasan 1,2 Pusat Listrik : Keramasan 18.3 Nov 2014 12 PLTG Borang 1 2 x 30 PLTG Borang 2 & 3 30 PLTMG Sewa Borang Pusat Listrik : Merah Mata 8 5 PGN Juni 2019 Interruptible Juni 2014 PLTG Talang Duku 1 35 PLTG Talang Duku 2 21 PLTG Talang Duku 3 Pusat Listrik : Talang DUku
Suplemen 6 Pola Operasi PLTG Talang Duku Pola operasi awal (gas : 8 BBTUD) Pola operasi dengan gas interruptible (gas : 13.8 BBTUD) 1 Des 2013 – 30 Juni 2014 PLTG #2 PLTG #3 PLTG #1