Upload presentasi
Presentasi sedang didownload. Silahkan tunggu
Diterbitkan olehSugiarto Kusuma Telah diubah "5 tahun yang lalu
1
Ismu Kusumanto Jurusan Teknik Elektro UIN Sultan Syarif Kasim Riau
ACTIVITY ON ARROW Ismu Kusumanto Jurusan Teknik Elektro UIN Sultan Syarif Kasim Riau
2
ACTIVITY ON ARROW ID ID Activity Duration/Time Event Slack Slack Early
Start Last Finish Slack Early Start Last Finish
3
EXAMPLE A None 5 B 15 C 10 D E B,C F B,C,D G 170 H E,G 35 Activity
Description Preceding Time A Application approval None 5 B Construction plans 15 C Traffic study 10 D Service availability check E Staff report B,C F Commission approval B,C,D G Wait for construction 170 H Occupancy E,G 35
4
ANSWER 4 E B A H C Y F G X 1 2 3 5 6 7 8 D
5
ANSWER 4 E B Y 15 15 X A H C F G 1 2 3 5 6 7 8 5 10 10 170 35 D 5
6
ANSWER 20 4 E B 15 15 Y 15 35 5 X 235 A 20 H C 15 F 30 G 200 1 2 3 5 6 7 8 5 10 10 170 35 10 D 5
7
20 4 E B 15 15 Y 15 35 5 X 235 A 20 H C 15 F 30 G 200 1 2 3 5 6 7 8 5 10 10 170 35 10 D 5
8
20 20 5 4 E B 15 15 Y 15 35 5 X 235 A 20 H C 15 F 30 G 200 1 2 3 5 6 7 8 5 10 10 170 35 10 15 20 30 200 235 D 5
9
ANSWER 20 20 5 4 E B 15 15 Y 15 35 5 X 235 A 20 H C 15 F 30 G 200 1 2 3 5 6 7 8 5 10 10 170 35 10 15 20 5 20 30 200 235 D 5
10
PROBLEM Activity Predecessor Time A None 4 B 5 C D 3 E C,D 6 F 2 G E,F
Selesaikanlah penjadwalan berikut dengan metode AOA Activity Predecessor Time A None 4 B 5 C D 3 E C,D 6 F 2 G E,F
11
Terima Kasih
Presentasi serupa
© 2024 SlidePlayer.info Inc.
All rights reserved.