1
Pertemuan Sub-Klaster SHELTER Shelter Sub-Cluster Meeting
6 November 2018 Wisma PMI lt. 5, IFRC Meeting Room
2
Agenda Pertemuan Meeting Agenda
Info terkini dari koordinator sub klaster Shelter Updated current information from Sub-Cluster Shelter Coordinator Info terkini dari tim Informasi Manajemen (5W, daftar kontak lembaga) Updated current information from IM (5W, Organisation Contact List) Info terkini dari kelompok kerja (SAG, TWIG) Updated current information from task force (SAG, TWIG) Info terkini dari Anggota Shelter Updated current information from Shelter members Topik-Topik penting lainnya Any Other Business
3
Two new members joining shelter sub-cluster team:
Pak Irvan assisting Hub Coordinator in Palu Pak Hijaz Information Management Coordinator They will go to Palu on Wednesday. Ridho is also joining assist with data collection and management.
4
Review Pertemuan Sebelumnya
Last Meeting Review Pertemuan di Jakarta : Meeting at Jakarta : Daftar baru barang-barang bantuan yang diminta / diterima dari luar negeri belum secara resmi diterbitkan. Namun sudah disebutkan bahwa tenda akan terus menjadi barang prioritas. The new list of requested/accepted relief items from overseas has not yet been officially published. But already mentioned that tents will continue to be priority items. Masih belum ada kejelasan berapa banyak Huntara yang sedang dibangun dan apa saja yang akan didukung oleh LSM dan siapa yang akan bertanggung jawab untuk menyediakan layanan (seperti sekolah, perawatan kesehatan, suplai pemberi peringatan, dll.) Untuk pemukiman Huntara. Kemensos memohon kepada LSM untuk mengisi kekosongan. It seems to still be unclear how many huntara are being built and to what extend there will be ask for support by NGOS and who will be in charge of providing services (like schools, healthcare, warner supply etc.) for Huntara settlements. Kemensos is appealing to NGOs to fill gaps.
5
Pertemuan di Palu : Meeting at Palu :
Aktivasi Person In Charge (PIC) di Dinas Sosial Provinsi untuk Klaster PP Activation of person in Charge at Dinsos at Provincial level for PP Cluster lead UN OCHA mengadakan Kajian Pasar Bersama (JMA), akan ada pertemuan hari selasa 6 November 2018 di Kantor Gubernur Sulteng UN OCHA is planning to conduct a Joint Market Assessment (JMA), there will be a briefing on tuesday, 6 November 2018 at Governor Office IOM akan melaksanakan pelatihan untuk koordinator pengungsian IOM will hold a training for camp coordination
6
Info Terkini dari Koordinator Sub Klaster Shelter
Updated current information from Sub-Cluster Shelter Coordinator Hasil Rapat Internal Terbatas 5 Nov 2018 High level Internal Meeting held by vice president, Nov 5, 2018 Penetapan wilayah merah : daerah rawan bencana yang tidak bisa di bangun dan ditinggali. Determine “Red Zone” the disaster-Prone zone where cannot be rebuild and inhabited Daerah relokasi : Dibutuhkan lahan ha utk daerah relokasi dampak bencana utk kk Relocation area: ha of land is needed for the disaster impact relocation are for HH Rencana relokasi mulai 2019, penataan infrastruktur huntap, fasum dan fasos. Relocation plans starting in 2019, infrastructure for permanent shelter, public facilities and social facilities Untuk Implementasi: PUPR meminta BMKG untuk melakukan pemetaan Rawan Bencana untuk menunjuk lokasi relokasi For Implementation: PUPR ask BMKG to do mapping for Disaster Prone to designate relocation sites Data up date pengungsi untuk kota Palu jiwa = KK Up-date data on displaced in the city of Palu people = 10,724 HH
7
Info terkini dari tim Manajemen Informasi (5W, daftar kontak lembaga)
Updated current information from Information Management (5W, organisation contact list) Penjelasan terkait form 5W terbaru Explanation if updated 5W format Form 5W
9
Laporan Form 5W 5W Form Reporting
Huntara Kolektif, direncanakan oleh beberapa perusahaan / CSR (Community Social Response) Huntara Collective planned by private sector CSR (Community Social Response) Huntara Huntara individual only planned by CWS,CRS,HEKS (Catholic Relief Service) 2.788, ongoing already 400 CWS
10
Info Terkini dari Kelompok Kerja (SAG, TWIG)
Updated current information from task force (SAG, TWIG) MDMC mengujicobakan proses persetujuan untuk pembangunan pemukiman T-shelter individual (terintegrasi dengan WASH, listrik, pengelolaan limbah, dan dukungan psikososial) sesuai dengan desain MDMC. PUPR akan mengeluarkan izin untuk pembangunan tempat penampungan, berdasarkan itu, walikota / bupati akan mengeluarkan surat otorisasi untuk hak guna lahan MDMC is piloting the approval process for construction of individual T-shelter settlements (integrated with WASH, electricity, waste management, and psychosocial support) according to MDMC design. PUPR will to issue permits for the construction of shelters, based on that, walikota/ bupati will issue an authorization letter for land use rights. Pertemuan SAG di Palu membahas untuk menghapus opsi rental supports dari standar minimum. Some discussions in Palu SAG whether rental support options can be removed from the minimum standards.
11
Info Terkini dari Anggota Klaster
Update from Cluster Partners Situasi di lapangan, rencana kedepannya… Situation on the ground, plans perspectives... Isu yang berkembang, kepentingan lainnya? Emerging Issues, concerns?
12
AOB, Langkah Selanjutnya...
AOB, Next Steps, Action Points... Pertemuan selanjutnya: Selasa 6 November 2018 – WITA, Ruangan Rapat Lt. 2 Dinas Sosial Prov Sulawesi Tengah, Jl. Muh Yamin, Palu Next meeting: Tuesday 6 November 2018 – WITA, Ruangan Rapat Lt. 2 Dinas Sosial Prov Sulawesi Tengah, Jl. Muh Yamin, Palu …