1 PT. GAKA KARYA ENGINEERING
CFSPPP-PLTU LAMPUNG (2 x 100 MW) PT. GAKA KARYA ENGINEERING RIGGING DEPARTMENT

2 RIGGING DEPARTMENT ANALYZE AND PLANED ACTIVITY FOR LIFTING AND ERECTION WORK

3

4 START B NEED DUO CRANE MONO CRANE TAILING DESIGN A DATA MATERIAL
DIMENSION WEIGHT REFERENCE 1. RIGGING BOOK 2. EQUIP. MANUAL 3. B Safety Standard 4. B manually lever operated hoist 5. Australian Standard, AS , Wire ropes 6. Australian Standard, AS , Wire ropes 7. NAVFAC P-307, Juni 2003 8. Construction Industry Crane Safety Summit, 2009 B NEED DUO CRANE Yes No MONO CRANE TAILING DESIGN A

5 A B Risk JSA Safe RIGGING PLAN ACTION CONTROL REPORT STOP

6 STEP-1 1.TAHAP PERTAMA, OBJECT YANG AKAN DI ANGKAT ADALAH GENERATOR UNIT 2 (BARAT) 2.INSTALL RAIL WAY FOR SLINDING. 3.MENURUNKAN GENARATOR DARI ATAS "GOLDEFER" 4.TAKE IT ON RAIL WAY. 5.READY TO SLIDING. 6.MOVE IT UNTIL MM OVER THAN BEFORE ON ELEVATION +500.

7 STEP-2 1.TAHAP KEDUA, OBJECT YANG AKAN DI ANGKAT ADALAH GENERATOR UNIT 1 (TIMUR) 2.MENURUNKAN GENARATOR DARI ATAS "GOLDEFER" 3.TAKE IT ON RAIL WAY. 4.READY TO SLIDING. 5.MOVE IT UNTIL TO CENTERLINE OF GENERATOR ON ELEVATION +500.

8 1.INSTALL RAIL WAY SEJAJAR DENGAN SUMBU GENERATOR.
STEP-3 1.INSTALL RAIL WAY SEJAJAR DENGAN SUMBU GENERATOR. 2.MOVE IT UNTIL 7000MM OVER THAN BEFORE.

9 STEP-4 1.INSTALL GANTRY CRANE FOR LIFTING GENERATOR UNIT 1 (TIMUR)

10 1.CONNECTED ALL CONNECTOR,
STEP-5 1.CONNECTED ALL CONNECTOR, 2.LIFT OBJECT UNTIL ELEVATION UP TO GROUND FLOOR, 3.MOVE OBJECT BY CRANE UNTIL POSITION (FROM BARAT TO TIMUR)

11 1.INSTAL SKIDDING UNIT KETGA DAN KEEMPAT DI KAKI TENGAH.
STEP-6 1.INSTAL SKIDDING UNIT KETGA DAN KEEMPAT DI KAKI TENGAH. 2.LEPASKAN KAKI PANJANG.

12 1.GESER OBJECT KE POSISI TARGET.
STEP-7 1.GESER OBJECT KE POSISI TARGET.

13 1.TURUNKAN OBJECT KE POSISI TARGET.
STEP-8 1.TURUNKAN OBJECT KE POSISI TARGET.

14 STEP-9 1.SLIDING GENERATOR UNIT 2 (BARAT) TO CENTER LINE ON GROUND FLOOR.

15 1.PREPARATION ACTIVITIES FOR GENERATOR UNIT 2 (BARAT)
STEP-10 1.PREPARATION ACTIVITIES FOR GENERATOR UNIT 2 (BARAT)

16 1.CONNECTED ALL CONNECTOR,
STEP-11 1.CONNECTED ALL CONNECTOR, 2.LIFT OBJECT UNTIL ELEVATION UP TO GROUND FLOOR, 3.MOVE OBJECT BY CRANE UNTIL POSITION (FROM TIMUR TO BARAT)

17 STEP-12 1.INSTAL SKIDDING UNIT KETGA DAN KEEMPAT DI KAKI TENGAH. 2.LEPASKAN KAKI PANJANG.

18 1.GESER OBJECT KE POSISI TARGET.
STEP-13 1.GESER OBJECT KE POSISI TARGET.

19 1.TURUNKAN OBJECT KE POSISI TARGET.
STEP-14 1.TURUNKAN OBJECT KE POSISI TARGET.

20 RIGGING DEPARTMENT LOGO
LIFT SWING MOVE DOWN In safety corridor THINK SAFE DO SAFELY SAFETY FIRST

21 PT. GAKA KARYA ENGINEERING
CFSPPP-PLTU LAMPUNG (2 x 100 MW) PT. GAKA KARYA ENGINEERING RIGGING DEPARTMENT