Presentasi sedang didownload. Silahkan tunggu

Presentasi sedang didownload. Silahkan tunggu

~ pertemuan 8 ~ Oleh: Ir. Abdul Hayat, MTI April 2009 [Abdul Hayat, Activity Resources Estimating, Semester Genap 2008/2009] 1 ACTIVITY RESOURCES ESTIMATING.

Presentasi serupa


Presentasi berjudul: "~ pertemuan 8 ~ Oleh: Ir. Abdul Hayat, MTI April 2009 [Abdul Hayat, Activity Resources Estimating, Semester Genap 2008/2009] 1 ACTIVITY RESOURCES ESTIMATING."— Transcript presentasi:

1

2 ~ pertemuan 8 ~ Oleh: Ir. Abdul Hayat, MTI April 2009 [Abdul Hayat, Activity Resources Estimating, Semester Genap 2008/2009] 1 ACTIVITY RESOURCES ESTIMATING

3 INTRODUCTION Resource planning involves determining what physical resources (people, equipment, materials) and what quantities of each should be used to perform project activities. It must be closely coordinated with cost estimating April 2009 2 [Abdul Hayat, Activity Resources Estimating, Semester Genap 2008/2009]

4 RESOURCE ALLOCATION On network planning, activities are arranged based on technological sequence alone Resource availability should be considered as constraints on the scheduling of the activities resource allocation is an essential part of planning April 2009 3 [Abdul Hayat, Activity Resources Estimating, Semester Genap 2008/2009]

5 CASE STUDY: IT PROJECT Pengembangan Sistem Informasi Akuntansi PT XYZ Sistem Informasi Akuntansi yang akan dikembangkan menggunakan paket sistem yang sudah tersedia di pasaran, berlabel SAD atau ORAGEL, atau yang sejenisnya. Jumlah user yang akan terlibat dalam penggunaan sistem ini sebanyak 20 users April 2009 4 [Abdul Hayat, Activity Resources Estimating, Semester Genap 2008/2009]

6 LATIHAN PEMBAHASAN List Aktifitas Pembuatan Network Diagram Identifikasi Resources yang diperlukan Pembuatan Jadwal Proyek Alokasi Resources ke dalam Aktifitas April 2009 5 [Abdul Hayat, Activity Resources Estimating, Semester Genap 2008/2009]

7 LIST AKTIFITAS AktifitasDeskripsi Aktifitas Durasi (minggu) Aktifitas sebelumnya ASetup Team Proyek2- BIdentifikasi User Requirements4A CPemilihan & Pengadaan Sistem8A DPemilihan & Pengadaan Hardware6A EInstalasi & Test Hardware1D FInstalasi Sistem Software Akuntansi2C,E GKustomisasi Sistem Sesuai User Requirements12B,F HSystem Testing2G ITraining for Users2H JMigrasi data12I KImplementasi/Produksi12J April 2009 6 [Abdul Hayat, Activity Resources Estimating, Semester Genap 2008/2009]

8 PEMBUATAN NETWORK DIAGRAM Mahasiswa dibagi ke dalam kelompok @5 orang Masing-masing kelompok membuat network diagram sesuai list aktifitas April 2009 7 [Abdul Hayat, Activity Resources Estimating, Semester Genap 2008/2009]

9 IDENTIFIKASI RESOURCES YANG DIPERLUKAN Aktif itas DeskripsiDurasi (minggu) Resource yg diperlukan PersonilPeralatanMaterialLainnya … ASetup Team Proyek2 BIdentifikasi User Requirements4 CPemilihan & Pengadaan Sistem8 DPemilihan & Pengadaan Hardware6 EInstalasi & Test Hardware1 F Instalasi Sistem Software Akuntansi2 G Kustomisasi Sistem Sesuai User Requirements12 HSystem Testing2 ITraining for Users2 JMigrasi data12 KImplementasi/Produksi12 April 2009 8 [Abdul Hayat, Activity Resources Estimating, Semester Genap 2008/2009]

10 PEMBUATAN JADWAL PROYEK AktifitasDeskripsi Aktifitas Minggu Ke- 12345678910 …… dst ASetup Team Proyek …… dst BIdentifikasi User Requirements …… dst CPemilihan & Pengadaan Sistem …… dst DPemilihan & Pengadaan Hardware …… dst EInstalasi & Test Hardware …… dst F Instalasi Sistem Software Akuntansi …… dst G Kustomisasi Sistem Sesuai User Requirements …… dst HSystem Testing …… dst ITraining for Users …… dst JMigrasi data …… dst KImplementasi/Produksi …… dst April 2009 9 [Abdul Hayat, Activity Resources Estimating, Semester Genap 2008/2009]

11 ALOKASI RESOURCES KE DALAM AKTIFITAS AktifitasDeskripsi Aktifitas Minggu Ke- 1234 …… dst ASetup Team ProyekRp. …… dst BIdentifikasi User Requirements Rp. …… dst CPemilihan & Pengadaan Sistem Rp. …… dst DPemilihan & Pengadaan Hardware Rp. …… dst EInstalasi & Test Hardware …… dst FInstalasi Sistem Software Akuntansi …… dst G Kustomisasi Sistem Sesuai User Requirements …… dst HSystem Testing …… dst ITraining for Users …… dst JMigrasi data …… dst KImplementasi/Produksi …… dst Total Kebutuhan Resources (Rupiah)Rp. April 2009 10 [Abdul Hayat, Activity Resources Estimating, Semester Genap 2008/2009]

12 LATIHAN ESTIMASI RESOURCES SELESAI April 2009 11 [Abdul Hayat, Activity Resources Estimating, Semester Genap 2008/2009]


Download ppt "~ pertemuan 8 ~ Oleh: Ir. Abdul Hayat, MTI April 2009 [Abdul Hayat, Activity Resources Estimating, Semester Genap 2008/2009] 1 ACTIVITY RESOURCES ESTIMATING."

Presentasi serupa


Iklan oleh Google