PLTU 2 X 3 MW NANGA PINOH SITE SELECTION with

Presentasi serupa


Presentasi berjudul: "PLTU 2 X 3 MW NANGA PINOH SITE SELECTION with"— Transcript presentasi:

1 PLTU 2 X 3 MW NANGA PINOH SITE SELECTION with
PLN WILAYAH KALBAR, PLN-E, PLN RANTING NANGA PINOH KALBAR 17-21 March 2007

2 Alternative Lokasi PLTU cont’d
(KAMBUT) Titik koordinat Latitude : 00o ’ S Longitude : 111o41.780’ E Wilayah administrative Desa Kambut, Kel. Beru, Kec. Nanga Pinoh, Kab. Melawi, Propinsi Kalimantan Barat ALTERNATIVE-2 (KAMBUT) Titik koordinat Latitude : 00o16.811’ N Longitude : 111o41.791’ E Wilayah administrative Desa Kambut, Kel. Beru, Kec. Nanga Pinoh, Kab. Melawi, Propinsi Kalimantan Barat ALTERNATIVE-3 (NANGKA KEBEBU) Titik koordinat Latitude : 00o21.719’ N Longitude : 111o50.706’ E Wilayah administrative Desa NangaKebebu, Kec. Nanga Pinoh, Kab. Malawi, Propinsi Kalimantan Barat

3 Summary of site selection
Weight Aspects Alternative-1 Kambut Alternative-2 Alternative-3 Nanga Kebebu Technical aspects 69.16 68.56 81.01 Socio-economic aspects 28 26 32 Environmental aspects 50.70 TOTAL 147.86 145.26 163.71 Berdasarkan analisa visual dan pembobotan maka lokasi PLTU Singkawang Baru adalah: Alternative-2 (Pantai Kura-Kura)

4 Peta GPS

5 Alternative Lokasi PLTU
Pelabuhan Kuala Pantai Pasir Panjang-2 On Going Transmission Line 150 kV Pantai Kura-Kura Pantai Gosong

6 On Going Transmission Line 150 KV
Gambaran Peta Lokasi Pantai Kura-Kura On Going Transmission Line 150 KV

7 PRAKIRAAN TOTAL KEBUTUHAN AIR PLTU
AIR PENDINGIN = m3/hari AIR DEMIN & SERVICE = m3/hari PRAKIRAAN TOTAL KEBUTUHAN BATUBARA SELAMA 1 HARI = Ton SELAMA 1 BULAN = Ton PRAKIRAAN KEBUTUHAN LAHAN UNTUK COAL YARD AKTIVE STORAGE SELAMA 10 HARI = 0,07 Ha DEAD STORAGE SELAMA 1 BULAN = 0,02 Ha PRAKIRAAN ABU YANG DIHASILKAN SELAMA 1 TAHUN = ,00 Ton LUAS LAHAN YANG DISEDIAKAN = ,04 Ha

8 FOTO KAMBUT-1

9 FOTO KAMBUT-2

10 FOTO KABEBU

11 FOTO PELABUHAN PERHUBUNGAN

12 Gelombang Ekstrim Tanjung Gondol
Secondary Data Gelombang Ekstrim Tanjung Gondol

13 Elevasi Penting Pasang Surut Tanjung Gondol
Hasil Penaksiran Selama 20 Tahun Nilai Elevasi-elevasi Penting (cm) Highest Water Spring (HWS) : 88.39 Jml. Kejadian 1 Mean High Water Spring (MHWS) 72.33 493 Mean High Water Level (MHWL) 29.79 12707 Mean Sea Level (MSL) -0.97 175320 Mean Low Water Level (MLWL) -33.76 12693 Mean Low Water Spring (MLWS) -55.33 Lowest Water Spring (LWS) -68.18 Nilai Elevasi-elevasi Penting diikatkan pada MSL 89.36 73.3 30.76 .00 -32.79 -54.36 -67.21 Tunggang Pasang:


Download ppt "PLTU 2 X 3 MW NANGA PINOH SITE SELECTION with"