3 Control Chart Selection Quality Characteristic variableattribute n>1? n>=10 or computer? x and MR no yes x and s x and R no yes defectivedefect constant.

Presentasi serupa


Presentasi berjudul: "3 Control Chart Selection Quality Characteristic variableattribute n>1? n>=10 or computer? x and MR no yes x and s x and R no yes defectivedefect constant."— Transcript presentasi:

1

2

3 3 Control Chart Selection Quality Characteristic variableattribute n>1? n>=10 or computer? x and MR no yes x and s x and R no yes defectivedefect constant sample size? p-chart with variable sample size no p or np yes constant sampling unit? c u yesno

4 Comparison of Variables v. Attributes Variables  Fit certain cases.  Both mean and variation information.  More expensive?  Identify mean shifts sooner before large number nonconforming. Attributes  Fit certain cases – taste, color, etc.  Larger sample sizes.  Provides summary level performance.  Must define nonconformity.

5

6 Types of Control Control ChartMonitors Attribute control charts p chart Process fraction defective c chart number of defects u chart defects per unit Variables control charts X-bar chart Process mean R chart (Range Chart) Process variability

7 When are Shifts Detected ? Lower Specification Limit LCLUCL Upper Specification Limit Process Target Nonconformity Control Chart Identifies Mean Shift Here Attribute Chart Identifies Mean Shift Here

8 Variables v. Attributes Both have advantages. At High levels - Attribute charts, identify problem areas. At Lower levels – Variables charts, quantitative problem solving tools.

9 Ch 12- Control Charts for Attributes p chart – fraction defective np chart – number defective c, u charts – number of defects

10 Defect vs. Defective ‘Defect’ – a single nonconforming quality characteristic. ‘Defective’ – items having one or more defects.

11 Legal Concerns with Term ‘Defect’ Often called ‘nonconformity’. Possible Legal Dialog  Does your company make a lot of ‘defects’?  Enough to track them on a chart ?  If they are not ‘bad’, why do you call them ‘defects’, sounds bad to me.  So you knowingly track and ship products with ‘defects’?

12 Summary of Control Chart Types and Limits Table 12.3 These are again ‘3 sigma’ control limits

13 p, np - Chart P is fraction nonconforming. np is total nonconforming. Charts based on Binomial distribution. Sample size must be large enough (example p=2%) Definition of a nonconformity. Probability the same from item to item.

14 c, u - Charts c and u charts deal with nonconformities.  c Chart – total number of nonconformities.  u Chart – nonconformities per unit. Charts based on Poisson distribution. Sample size, constant probabilities.

15

16

17

18

19 How to Interpret Attribute Charts Points beyond limits- primary test.  Below lower limits means process has improved. Zone rules do not apply. Rules for trends, shifts do apply. Only get One Chart !!

20 Examples of When to Use p,np charts–  Number of nonconforming cables is found for 20 samples of size 100.  Number of nonconforming floppy disks is found for samples of 200 for 25 trials. c,u charts-  Number of paint blemishes on auto body observed for 30 samples.  Number of imperfections in bond paper – by area inspected and number of imperfections.

21 p-chart Jika bohlam tidak menyala, lampu yang rusak Perusahaan ingin  Perkirakan persentase bohlam rusak dan  Tentukan apakah persentase bohlam rusak terus meningkat dari waktu ke waktu.. Sebuah peta kendali p adalah alat yang sesuai untuk menyediakan perusahaan dengan informasi ini.

22 Notation Sample size = n = 100 Number of samples (subgroups) = k = 5 X = number of defective bulbs in a sample p = sample fraction defective = ??? p-bar = estimated process fraction defective P = process fraction defective (unknown) p-bar is an estimate of P

23 Inspection Results

24 Compute p and p-bar

25 p-bar (Estimated Process Fraction Defective)

26 p-Chart Control Limits

27 p-Chart - Control Limits

28

29 Interpretation The estimated fraction of defective bulbs produced is.23. On Day 2, p was below the LCL. This means that a special cause occurred on that day to cause the process to go out of control. The special cause shifted the process fraction defective downward. This special cause was therefore favorable and should be ???

30 Interpretation After Day 2, the special cause lost its impact because on Day 4, the process appears to be back in control and at old fraction defective of.23. Until the special cause is identified and made part of the process, the process will be unstable and unpredictable. It is therefore impossible to obtain a statistical valid estimate of the process fraction defective because it can change from day to day.

31 UCL LC L p-Chart Process fractions defective is shifting (trending) upward Sampling Distribution P = process fraction defective P P P P Trend Within Control Limits

32 Applications Think of an application of a p-chart in:  Sales  Shipping department  Law

33 Use of c-Charts When we are interested in monitoring number of defects on a given unit of product or service.  Scratches, chips, dents on an airplane wing  Errors on an invoice  Pot holes on a 5-mile section of highway  Complaints received per day Opportunity for a defect must be infinite. Probability of a defect on any one location or any one point in time must be small.

34 c-Chart c-chart notation: c = number of defects k = number of samples

35 c-Chart A car company wants to monitor the number of paint defects on a certain new model of one of its cars. Each day one car in inspected. The results after 5 days are shown on the next slide.

36 c-Chart

37 c-Chart - Mean

38 c-Chart – Control Limits

39

40

41 Conclusion Process shows upward trend. Even though trend is within the control limits, the process is out of control. Mean is shifting upward This is due to an unfavorable special cause. Must identify special cause and eliminate it from process. Who is responsible for finding and eliminating special cause?

42 Mini Case Think of an application of a c-chart bank.

43 u-Chart With a c chart, the sample size is one unit. A u-chart is like a c-chart, except that the sample size is greater than one unit. As a result, a u-chart tracks the number of defects per unit. A c-chart monitors the number of defects on one unit.

44 u-Chart A car company monitors the number of paint defects per car by taking a sample of 5 cars each day over the next 6 days. The results are shown on next side.

45 u-Chart

46

47

48

49

50 Conclusion The process appears stable. We can therefore get a statistically valid estimate the process mean number of defects per car. Our estimate of the mean number of paint defects per car is 10.5, the center line on the control chart. Thus, we expect each car to have, on average, 10.5 paint defects.

51 Conclusion Although the process is stable, the number of defects per car is too high. Deming calls this a stable process for the production of defective product. Important take away:  A stable process (process in control) is not necessarily a good process because it can be in control at the wrong level.  A stable process is predictable, but this doesn’t mean that what is being predicted is favorable.

52 Mini Case Who is responsible for improving this process? What is required to improve the process?

53 u-Chart vs. c-Chart If n = 1, u = c and Control limits of the two chart will therefore be the same.

54 Sample Size Control ChartWhen To UseSample Size p-ChartMonitor the proportion of defectives in a process At least 50 c-ChartMonitor the number of defects 1 u-chartMonitor the number of defects per unit >1

55 In Practice You need 25 to 30 samples before computing initial control limits. When a special cause occurs, you should eliminate that sample and re-compute control limits if  Special cause is identified  Eliminated or made part of process To identify special causes, workers must keep log sheet, where they record any changes they make to the process.

56 Tracking Improvements UCL LCL UCL Process not centered and not stable Process centered and stable Additional improvements made to the process

57 Sampel SAMA…p chart Proporsi diketahui Garis Tengah = p¯

58 Sampel SAMA…p chart Proporsi TIDAK diketahui m nomer sampel (vertikal) n ukuran sampel (horisontal) D bagian tidak sesuai p¯= ∑Di/(mn) Garis Tengah = p¯

59 Sampel BEDA … a. Metode INDIVIDU  Batas Kendali tergantung ukuran sample tertentu shg BKA/BKB tidak berupa garis LURUS b. Metode RATA_RATA  Ukuran sampel RATA - RATA dg perbedaan tidak terlalu besar ( n¯ = ∑n/observasi) c. Peta Kendali TERSTANDAR dg GT=0 dan BK ± 3

60 np Chart Note: If computed LCL is negative, set LCL = 0 assuming: np > 5 n (1- p ) > 5

61 c-chart dan u-chart Mengetahui banyaknya kesalahan unit produk sbg sampel Sampel konstan  c-chart Sampel bervariasi  u-chart Aplikasi : bercak pd tembok, gelembung udara pd gelas, kesalahan pemasangan sekrup pd mobil

62 Number of defects per unit: c¯ = ∑ ci / n C - chart

63 U-chart u¯ = ∑ ci/n n ¯ = ∑ ni/g g = banyaknya observasi Model Individu BPA-u = u¯ + 3 √ (u¯ /ni) BPB-u = u¯ - 3 √ (u¯ /ni) Model Rata-rata BPA-u = u¯ + 3 √ (u¯ /n¯) BPB-u = u¯ - 3 √ (u¯ /n¯)

64 Warning Conditions….. Western Electric : 1. 1 titik diluar batas kendali ( 3σ) 2. 2 dr 3 titik berurutan diluar batas kend64li (2σ) 3. 4 dr 5 titik berurutan jauh dari GT (1σ) 4. 8 titik berurutan di satu sisi GT 5. Giliran panjang 7-8 titik 6. 1/beberapa titik dekat satu batas kendali 7. Pola data TAK RANDOM

65 Patterns to Look for in Control Charts

66 Twenty samples, each consisting of 250 checks, The number of defective checks found in the 20 samples are listed below. (proporsi tidak diketahui) Example………p-np chart $ Simon Says Augusta, ME 01227

67 Note that the computed LCL is negative. Estimated p = 80/((20)(250)) = 80/5000 =.016 Control Limits For a p Chart $ Simon Says Augusta, ME 01227

68 Tdk sesuai Proporsi Proporsi (4/250) = 0,016 (1/250) =0, (2/250) = 0,008 (8/250) = 0,032

69 p Chart for Norwest Bank Sample Number Sample Proportion p UCL LCL Control Limits For a p Chart $ Simon Says Augusta, ME 01227

70 Ukuran sampel sama = 50 ( p-chart) no Banyak produk cacat no

71 n = m = D = p¯= BKA= BKB = Tabel proporsi untuk plot ke grafik

72 n = 50 m = 20 D = 72 p¯= 72 / (20.50) =.072 p= √ (0,072)(0,928)/50 =.037 BKA= 0, (0,037)= 0,183 BKB = 0, (0,037) = -0,039 = 0 Tabel proporsi untuk plot ke grafik

73 Ukuran sampel sama = 50 ( p-chart) cacatproporsicacatproporsi (4/50 ) = 0,08 (2/50) = 0, (5/50) = 0,01 (10/50) = 0,20 (out)  revisi (4/50) = 0,08 (3/50) = 0,06

74 Revisi p¯ = (72-10) / ( ) = 62/950 = 0,065 p = √ (0,065)(0,935)/50 = 0,035 BKA = 0, (0,035) = 0.17 BKB = 0, (0,035) = -0,04 = 0 Grafiknya juga berubah

75 Ukuran sampel beda (p chart) nosampel Produk cacat nosampel Jmlsampel4860JmlCacat341

76 Metode Rata-rata Sampel rata-rata n¯ = total sampel /observasi = 4860/20 = 243 p¯ = D/(n¯m) = 341 / (243.20) = 0,07 (CL) p = √ (0,07(0,93))/243 = 0,0164 BPAp = 0, (0,0164) = 0,119 BPBp = 0, (0,0164) = 0,021

77 Metode Individu Sampel rata-rata n¯ = total sampel /observasi = 4860/20 = 243 p ¯= D/(n¯m) = 341 / (243.20) = 0,07 (CL) semua titik sama BP (obs-1) p = √ (0,07(0,93))/200 = 0,018 BPA = 0, (0,018) = 0,124 BPB = 0, (0,018) = 0,016……………….dst

78 Tabel Proporsi untuk Grafik No observasi sampelcacatproporsi ,0700,0550,0850,067………………………………0,0950,0500,0550,067

79 Example…c-chart no Byknya kesalahan no

80 c¯ = ∑c/n = 152/20 = 7,6 BPA c = (7, 6) + 3 (√7,6) = 15,87 BPB c = (7, 6) - 3 (√7,6) = -0,67 = 0

81 Example…u-chart noSampelcacatnosampelcacat

82 Metode Rata-rata Sampel Rata-rata u¯ = 192/415 = 0,462 (CL) n¯ = 415/20 = 20,75 BPAu = (0,462) + 3 √ (0,462/20,75) = 0,906 BPBu = (0,462) - 3 √ (0,462/20,75) = 0,018

83 Metode Individu Sampel Rata-rata u¯ = 192/415 = 0,462 (CL) n¯ = 415/20 = 20,75 Batas Kendali Observasi -1 BPA-1 = (0,462) + 3 √ (0,462/20) = 0,916 BPB-1 = (0,462) - 3 √ (0,462/20) = 0,008…….dst