PERTEMUAN 12 METODE HARGA POKOK PROSES 2 DEPARTEMEN DOSEN PEMBINA ONY WIDILESTARININGTYAS,SE.,MSi.
PENGOLAHAN PRODUK MELALUI 2 DEPARTEMEN APABILA PROSES PENGOLAHAN BARANG MELALUI DUA DEPARTEMEN PRODUKSI ATAU LEBIH, MAKA LAPORAN BIAYA PRODUKSI DIBUAT PER DEPARTEMEN PRODUKSI.
KASUS PT SURYATEX MEMPRODUKSI TEKSTIL MELALUI DUA DEPARTEMEN PRODUKSI YAITU DEPARTEMEN A DAN DEPARTEMEN B. BERIKUT DATA PRODUKSI DAN DATA BIAYA PRODUKSI SELAMA BULAN JANUARI 2008.
DATA PRODUKSI DEPT A DEPT B PRODUK MASUK PROSES 1000 KG 800 KG PRODUK SELESAI DITRANSFER KE DEPT B - PRODUK SELESAI DITRANSFER KE GUDANG 650 KG PRODUK DALAM PROSES AKHIR TINGKAT PENYELESAIAN : BIAYA BAHAN 100%, BIAYA KONVERSI 60% 200 KG BIAYA BAHAN 100%, BIAYA KONVERSI 70% 150 KG
DATA BIAYA PRODUKSI DEPT A DEPT B BIAYA BAHAN $ 120.000 $ 64.000 BIAYA TENAGA KERJA $ 184.000 $ 188.750 BIAYA OVERHEAD PABRIK $ 138.000 $ 113.250 TOTAL $ 442.000 $ 366.000
DIMINTA : SUSUNLAH LAPORAN BIAYA PRODUKSI DEPARTEMEN A. SUSUNLAH LAPORAN BIAYA PRODUKSI DEPARTEMEN B. BUATLAH JURNAL TRANSAKSI DIATAS.
PT. SURYATEX LAPORAN BIAYA PRODUKSI DEPARTEMEN A BULAN JANUARI 2008 DATA PRODUKSI JUMLAH PRODUK YANG MASUK PROSES 1.000 KG JUMLAH PRODUK SELESAI YANG DITRANSFER KE DEPARTEMEN B 800 KG JUMLAH PRODUK DALAM PROSES AKHIR TP : BIAYA BAHAN 100% , BIAYA KONVERSI 60% 200 KG 1000 KG TOTAL
BIAYA PRODUKSI YANG DIBEBANKAN DEPT A ELEMEN BIAYA 1 PRODUK EKUIVALEN (KG) 2 JUMLAH BIAYA ($) 3 BIAYA/KG ($) 4 = 3 : 2 B.BAHAN 800+200(100%)=1000 120.000 120 B.TENAGA KERJA 800+200(60%)=920 184.000 200 B.OVERHEAD PABRIK 138.000 150 TOTAL 442.000 470
PERHITUNGAN HARGA POKOK DEPT A HARGA POKOK PRODUK SELESAI YG DITRANSFER KE DEPT.B 800 KG X @$470 $ 376.000 HARGA POKOK PRODUK DALAM PROSES AKHIR BULAN BIAYA BAHAN 200KG (100%) X @ $120 $ 24.000 BIAYA TENAGA KERJA 200KG (60%) X @ $200 BIAYA OVERHEAD PABRIK 200KG (60%) X @ $150 $ 18.000 $ 66.000 JUMLAH BIAYA PRODUKSI $ 442.000
PT. SURYATEX LAPORAN BIAYA PRODUKSI DEPARTEMEN B BULAN JANUARI 2008 DATA PRODUKSI JUMLAH PRODUK YANG MASUK PROSES 800 KG JUMLAH PRODUK SELESAI YANG DITRANSFER KE GUDANG 650 KG JUMLAH PRODUK DALAM PROSES AKHIR TP : BIAYA BAHAN 100% , BIAYA KONVERSI 70% 150 KG TOTAL
BIAYA PRODUKSI YANG DIBEBANKAN DEPT B JUMLAH BIAYA ($) BIAYA/KG ($) HARGA POKOK DARI DEPT.A 376.000 470 BIAYA YG DITAMBAHKAN DIDEPT B. : ELEMEN BIAYA 1 PRODUK EKUIVALEN (KG) 2 3 4 = 3 : 2 B.BAHAN 650+150(100%)=800 64.000 80 B.TENAGA KERJA 650+150(70%)=755 188.750 250 B.OVERHEAD PABRIK 113.250 150 366.000 480 TOTAL BIAYA PRODUKSI 742.000 950
PERHITUNGAN HARGA POKOK DEPT B HARGA POKOK PRODUK SELESAI YG DITRANSFER KE GUDANG 650 KG X @$950 $ 617.500 HARGA POKOK PRODUK DALAM PROSES AKHIR BULAN HARGA POKOK DARI DEPT.A 150KG X @$470 $ 70.500 BIAYA BAHAN 150KG (100%) X @ $80 $ 12.000 BIAYA TENAGA KERJA 150KG (70%) X @ $250 $ 26.250 BIAYA OVERHEAD PABRIK 150KG (70%) X @ $150 $ 15.750 $ 124.500 JUMLAH BIAYA PRODUKSI $ 742.000
JURNAL Mencatat biaya produksi DEPT.A (dalam $.) DATE ACCOUNTS REF DEBET CREDIT 31 JAN 08 BARANG DALAM PROSES-BIAYA BAHAN - DEPT.A 120.000 - BARANG DALAM PROSES-BIAYA TENAGA KERJA – DEPT.A 184.000 BARANG DALAM PROSES-BIAYA OVERHEAD PABRIK – DEPT. A 138.000 PERSEDIAAN BAHAN GAJI & UPAH MACAM-MACAM REKENING YG DIKREDIT
Jurnal (Mencatat produk selesai DEPT. A yg ditransfer ke DEPT B Jurnal (Mencatat produk selesai DEPT.A yg ditransfer ke DEPT B.) (Dalam $) DATE ACCOUNTS REF DEBET CREDIT 31 JAN 08 BARANG DALAM PROSES - BIAYA BAHAN – DEPT.B 376.000 - BARANG DALAM PROSES- BIAYA BAHAN – DEPT.A 96.000 BIAYA TENAGA KERJA – DEPT.A 160.000 BIAYA OVERHEAD PABRIK – DEPT.A 120.000
Jurnal (Mencatat produk dalam proses akhir DEPT.A) (Dalam $) DATE ACCOUNTS REF DEBET CREDIT 31 JAN 08 PERSEDIAAN PRODUK DALAM PROSES – DEPT.A 66.000 - BARANG DALAM PROSES- BIAYA BAHAN – DEPT.A 24.000 BIAYA TENAGA KERJA – DEPT.A BIAYA OVERHEAD PABRIK – DEPT.A 18.000
JURNAL Mencatat biaya produksi DEPT.B (dalam $.) DATE ACCOUNTS REF DEBET CREDIT 31 JAN 08 BARANG DALAM PROSES-BIAYA BAHAN - DEPT.B 64.000 - BARANG DALAM PROSES-BIAYA TENAGA KERJA – DEPT.B 188.750 BARANG DALAM PROSES-BIAYA OVERHEAD PABRIK – DEPT. B 113.250 PERSEDIAAN BAHAN GAJI & UPAH MACAM-MACAM REKENING YG DIKREDIT
Jurnal (Mencatat produk selesai DEPT. B yg ditransfer ke GUDANG Jurnal (Mencatat produk selesai DEPT.B yg ditransfer ke GUDANG.) (Dalam $) DATE ACCOUNTS REF DEBET CREDIT 31 JAN 08 PERSEDIAAN PRODUK JADI 617.500 - BARANG DALAM PROSES- BIAYA BAHAN – DEPT.B 357.500 BIAYA TENAGA KERJA – DEPT.B 162.500 BIAYA OVERHEAD PABRIK – DEPT.B 97.500
Jurnal (Mencatat produk dalam proses akhir DEPT.B) (Dalam $) DATE ACCOUNTS REF DEBET CREDIT 31 JAN 08 PERSEDIAAN PRODUK DALAM PROSES – DEPT.B 124.500 - BARANG DALAM PROSES- BIAYA BAHAN – DEPT.B 82.500 BIAYA TENAGA KERJA – DEPT.B 26.250 BIAYA OVERHEAD PABRIK – DEPT.B 15.750
ISTILAH ASING PRODUK DALAM PROSES = WORK IN PROCESS PRODUK JADI = FINISHED GOOD BIAYA BAHAN = MATERIAL COST BIAYA TENAGA KERJA = PAYROLL COST BIAYA OVERHEAD PABRIK = FACTORY OVERHEAD COST PERSEDIAAN PRODUK DALAM PROSES = WORK IN PROCESS INVENTORY PERSEDIAAN PRODUK JADI = FINISHED GOOD INVENTORY PERSEDIAAN BAHAN = MATERIAL INVENTORY GAJI & UPAH = PAYROLL MACAM-MACAM REKENING YG DIKREDIT = VARIOUS CREDIT
TERIMA KASIH